Saturday, February 27, 2016

Mumbai Monorail project cost escalated by Rs95 crore: RTI

DNA: Mumbai: Saturday, February 27, 2016.
Although the Mumbai metropolitan region development authority (MMRDA) was in denial, but the cost of Mumbai Monorail project has already escalated by around Rs95 crore.
Since the project took off in 2008, till March 2015, there has been an increase of cost by Rs22.78 crore.
As on January 2016, the MMRDA has spent a total of Rs2,554.81 crore on both the phases of the project as against the initial cost of Rs2,460 crore. Thus, the price hike till now has been Rs94.81 crore and it is likely to increase further in the months to come.
As per the data, under RTI, available with dna, in the financial year 2013-14 the cost overrun was Rs18,82,96,992 and Rs3,95,80,924 in following fiscal year of 2014-15.
However, the precise cost escalation will be calculated once both the phases of Mumbai Monorail (Phase-1 Chembur-Wadala Depot and Phase-2 Wadala Depot-Jacob Circle) will be completed and only after the project gets ready for passenger operations by September-October. But an official shared that the price variation is likely to be around 15 per cent.
In the last two years, or since inauguration on February 1, 2014, the MMRDA has spent Rs17,18,84,322 on operation and maintenance of the monorail trains between Chembur and Wadala Depot.
The initial deadline for the ambitious and prestigious project was December 2010 (first phase Wadala to Chembur) and May 2011 for Wadala to Jacob Circle. But the project has witnessed repeated deadline revisions.
Two years ago, senior MMRDA officials claimed that despite the delay, the project cost has never been escalated from Rs 2,460 crore. In 2008, MMRDA had estimated the 19.54-km long project's cost at Rs1,440 crore, which was very low according to private players and during bidding stage it was revised to Rs2,460 crore.
HEADS AMOUNT (in Rs)
Bills 22,40,99,89,926, Operation & Maintenance 17,18,84,322, Utility 35,08,02,176, Customs Duty 1,09,43,70,977, Octroi 51,22,70,559, Value Added Tax 45,99,51,389, Service Tax 32,10,03,344, Escalation 22,78,77,916, TOTAL 25,54,81,50,609