Indian
Express: Mumbai: Friday, 24 July 2015.
A
government-appointed committee has recommended a hike in the tariff of the
city’s first Metro, with the operator in the red, documents obtained under the
Right to Information (RTI) Act show the Reliance Infrastructure-led operator,
Mumbai Metro One Pvt Ltd (MMOPL), had in its initial bid for the project shown
willingness to bear losses till 2018.
According to
information sought by RTI activist Anil Galgali from the Mumbai Metropolitan
Region Development Authority (MMRDA), the MMOPL had expected to complete work
on the Versova-Andheri-Ghatkopar Metro in 2010.
Going by the
information provided to Galgali, the MMOPL had assumed losses for eight years,
till 2018.
The MMOPL is
a consortium of Reliance Infrastructure, Veolia Transport and the MMRDA, which
has a 26 per cent stake in the venture.
The company
has constructed the 11.4-km Versova-Andheri-Ghatkopar Metro on a public-private
partnership model. It has been locked in a dispute with the MMRDA over the
structure fare after the project cost ballooned to Rs 4,321 crore from the
original Rs 2,356 crore.
After
slugging it out in the Bombay High Court and the Supreme Court, a Union
government-appointed fare fixation committee was formed to look into the tariff
revision according to the Metro Act.
Citing high
cost of construction and lack of parity with other Metro projects owing to it
being the country’s first such corridor built on a PPP model, the committee
recommended a fare of Rs 10-110, up from the current Rs 10-40.
Galgali said,
“In the business plan submitted by Reliance Infrastructure, it was estimated
that the company will require eight years to break even in this project, and
hence had planned to sustain a loss up to 2018. Instead of sticking to its
business plan, right from Day One the company started cribbing about the loss.”
The MMOPL
said the RTI reply was based on incomplete information.
A company
spokesperson said, “The fare fixation committee has considered all aspects of
the cost to operate the line, including long-term sustainability of the
project. In our final financial bids to MMRDA with a viability gap funding
(VGF) of Rs 650 crore, we had not envisaged any cash loss even in the first
year of operation.”
The original
bid was on the assumption of a VGF of Rs 1,250 crore, which was later brought
down to Rs 650 crore after negotiations.
VGF refers to
the government’s contribution in a PPP project to make it viable.
An MMOPL
official said the financial projections, which the MMRDA had released in
response to the RTI application, did not assume any VGF and were based on the
entire project cost of Rs 2,356 crore.