Cost of Ahmedabad-Mumbai bullet train project nearly doubles to Rs 2 lakh crore: RTI

Deccan Herald: Ahmedabad: Wednesday, 18 November 2026.
The project has been delayed substantially over various issues, including compensation for land acquisition, among others.

Construction site on the Mumbai-Ahmedabad Bullet Train corridor, in Gujarat's Anand.Credit: PTI Photo

The National High Speed Rail Corporation Ltd (NHSRCL) has spent Rs 92,761 crore on the Ahmedabad-Mumbai high-speed rail corridor (MAHSR) as of March 2026, while the cost of the ambitious project has nearly doubled, an RTI response has revealed.
The revised estimated cost of MAHSR, popularly known as the bullet train project, has increased to Rs 2,02,797 crore, nearly double the initial estimate of Rs 1,08,000 crore. The 508-km corridor passes through Maharashtra, Gujarat, and the Union Territory of Dadra & Nagar Haveli.
The project has been delayed substantially over various issues, including compensation for land acquisition, among others.
In response to an RTI query filed by a DH reporter, the NHSRCL said the project was originally targeted for completion by 2023. However, the anticipated completion timeline "can be ascertained after award of all contract packages," the reply said in response to a question about a tentative timeline for completion of the project.
On query whether the proposed combination of Japanese track technology, non-Japanese signalling and India-built trains was part of the original project design, the response stated that "it was planned to start the operation using Japanese Shinkansen Rolling Stock." However, it has been decided to start operation using an indigenously developed trainset, it added.
Queries related to copies of correspondence between the government of India and Japan over reported disagreements over procuring signalling systems were denied, citing, "the sharing of these documents is restricted as covered under Non-Disclosure Agreement between both the governments."
On the question of delivery schedule for trains and their revised delivery schedule, the reply stated that "the dispatch of the first indigenous trainset from BEML Ltd is planned in February 2027. Subsequent trainsets shall follow."
NHSRCL refused to provide records of whether the Japanese government approved or objected to the use of India-manufactured trains, saying that such records can't be provided as per Section 9 (1) (f) of the RTI Act. This clause exempts the government from disclosing information received in confidence from a foreign government.