Share all details related to Nal Se Jal scheme on website, WASMO told: Written by Parimal A Dabhi

Indian Express: Ahmedabad: Tuesday, 1 October 2024.
Gujarat Information Commission (GIC) has ordered the Water and Sanitation Management Organisation (WASMO) to put all the details related to Nal Se Jal scheme in Gujarat from its beginning till 2023-24 on its website as a Proactive Disclosure (PAD) under the provisions of the Right to Information (RTI) Act. In its order dated September 4, the Commission observed that it has passed the order so that every citizen of Gujarat can get details of works done under Nal Se Jal scheme in their villages.
State Information Commissioner Nikhil Bhatt passed the order while acting on an appeal moved by Paresh Patel, a resident of Kelod in Bharuch district. Patel had moved an application under the provisions of the RTI Act before the public information officer of WASMO district unit in Bharuch while seeking Nal Se Jal scheme-related information for the entire district.
Patel said he was provided partial information while stating that the remaining information can be received from the water committee of gram panchayats. Patel first moved an appeal before the appellate authority Executive Engineer of Gujarat Water Supply and Sewerage Board in Bharuch district. However, he was informed that the information sought by him pertains to WASMO’s Gandhinagar office and so, he should submit an appeal before the WASMO office in the state capital.
Patel then moved a second appeal before the State Information Commission.
Citing a verdict of the Supreme Court and instructions given by the Central government, the Commission ordered that the information sought by the applicant cannot be provided since he has sought detailed and “huge” information of WASMO’s work done in all the villages of Bharuch district between 2019 and 2023.
It also said that providing such broad information will result in disproportionate usage of government resources. However, the Commission then stated that under the provisions of the RTI Act, WASMO is a public authority and it has not put information related to government schemes on its website as a proactive disclosure as per the rules of the RTI Act.
Citing a Supreme Court order on proactive disclosures to be made by public authorities on their websites under the provisions of Section 4 of the RTI Act, GIC, in its order, stated, “As per prevalent instructions, information of entire state (district wise, taluka-wise and village-wise with the help of drill down menu) was to be put on the website of WASMO by June 30, 2024. And accordingly, the latest schematic information has not been made available on the website of WASMO.”
It further stated: “In these circumstances, to ensure availability of information to all the citizens of Gujarat as to what work has been done in their villages under WASMO’s Nal Se Jal scheme, all information from the beginning of the scheme till financial year 2023-24 will have to be put on the website within 30 days of receiving this order. And this information will have to be updated at regular intervals as per rules.”
Section 4 of the RTI Act deals with obligations of public authorities under the law.
The GIC has also stated that it is WASMO’s responsibility to put all the information mentioned under Section 4 of RTI Act on its website under the title of “proactive disclosure”.
The Commission has also ordered that once the data is shared, it should be widely publicised so that people can be aware of the work done in their villages under the scheme.