Times
of India: Kolhapur: Saturday, 09 January 2016.
An RTI
application has revealed that the cost of the court complex on Kasba Bawada
road doubled from Rs 28 crore to Rs 55.08 crore due to the delay in completing
the project.
Civic
activist Dilip Desai, who filed the application, said that as per the work
order, the construction was supposed to be completed by August 2011.
The project
was approved in 2007 and the public works department issued the work order to
the private contractor in August 2009. The PWD had granted the construction
tender to a private company based on the terms that it (the company) will
finish the work in 24 months.
The complex
has been awaiting inauguration for the last four months. PWD officials
confirmed on at least two occasions that the budget was extended from the
original provision of Rs 28 crore.
"The PWD
failed to clarify why the project was delayed which resulted in cost
escalations. In the end, the taxpayers' money is wasted and PWD has taken no
action against the contractor," he said.
The activist
wrote a letter this week to the principal accountant general of Maharashtra to
conduct a thorough inquiry into the cost escalation and sought the attention of
the auditor to the multiple extensions granted to the contractor. "Even
though a three-year extension expired on August 2014, the project was declared
complete in September 2015. There was no report of action taken against the contractor,"
Desai wrote to the auditor.
Desai had
also written a memorandum on January 5 to the Kolhapur Municipal Corporation
and other government agencies attracting their attention to the case. He asked
the officers whether the inquiry into building permission has been completed.
He had earlier
alleged that the PWD had constructed the building without taking permission
from town planning department and had not obtained environmental clearance. The
PWD officials have declined to comment on the issue.