Indian
Express: Bhubaneshwar: Monday, 14 December 2015.
Sixteen
months after a portion of the bridge over River Mahanadi collapsed, report of
the technical committee, which was inquiring into the incident, remains
incomplete, if a reply from the Works Department to an RTI query is to be
believed.
Responding to
an RTI application by Arabinda Mohapatra who sought the technical committee
report, Superintending Engineer, Nabard (RIDF), Project Management Unit of
World Bank Projects, also the PIO, stated that the inquiry is incomplete and
hence the query can be answered only after submission of the report.
On August 27,
a portion of 2077 metre long bridge, linking Jatamundia with Subarnapur under
Athgarh, had collapsed leaving at least 13 workers injured.
While Chief
Minister Naveen Patnaik, also Works Minister, had expressed serious concern
about the incident, the Department constituted a four-member committee headed
by Chief Engineer (Civil) to probe and submit a report.
While the
bridge work is almost complete, what is baffling is that the technical
committee report is yet to be submitted because that would have pointed at the
flaws that led to the collapse.
“Had the
report been submitted on time, the Government would have been in a position to
understand reasons behind the collapse and acted to rectify the mistakes. Now,
nothing can be done,” sources in the Works Department said.
The
non-submission of the technical committee’s report even after a year has raised
serious question marks on the Department’s intent in plugging the loopholes.
Incidentally,
the Jatamundia collapse was the second such incident of the bridge project,
work for which had started in 2008.
The bridge
project, funded by the Nabard under its RIDF Scheme, was initially estimated at
`54.72 crore but a time-overrun led to escalation in cost to over `62 crore.
It is not the
only project which is running behind schedule.
The crucial
bridge over Kathajodi river, connecting CDA to Trishulia, has lagged too. This,
despite the Works Department issuing an office memorandum in November, 2013 to
increase efficiency and transparency of projects under which contractors can
avail an incentive ranging from one per cent to 10 per cent of the contract
value for completing work before the stipulated date of completion.