The Asian Age: Mumbai: Thursday,
January 30, 2014.
An RTI query
has revealed that the reason behind the three-year delay in Monorail is
primarily due to change of alignment of its route, which led to further cost
escalation of the project. The RTI query has also revealed that this and issues
of cost escalation were not presented before the chief minister and the Urban
Development Department of the Government of Maharashtra.
The query
regarding the change in route alignment of the Monorail project was raised by
RTI activist Anil Galgali. Mr Galgali was given a reply by the deputy planner
of the Monorail stating that the MMRDA commissioner, during his initial
inspection itself, had suggested exploring the possibility of an alternative
alignment, avoiding the Haffkinne Institute and Bhoiwada route.
Based on this suggestion, the feasibility of
an alternative alignment through Acharya Donde Marg-Khanolkar Chauk-Tata
hospital was explored and it was approved later on by the commissioner. This
proposed realignment is 1.1 km-long as against the existing alignment of 0.717
km. The overall increase in the alignment amounts to 383 metres.
MMRDA wrote a letter to the BMC chief engineer
informing him about the decision of realignment stating that the route is now
slightly modified due to serious Right of Way (ROW) constraints, requiring
demolition of around 60 pucca legal structures on G.D. Ambedakar Marg from Gora
Kumbhar chauk.
“This did not fit into the stipulated time
schedule of the project. Therefore the alignment had to be changed. The route
takes a left from Kumbhar Chauk on Acharya Donde Marg and E. Borges Marg and
meets again at Mane Master Chauk. The decision of this alignment was taken
jointly by the municipal commissioners of both the MMRDA and the BMC,” the
letter said.
When asked about the cost escalation this
project had to bear because of the re-aligned route, the Monorail authorities
replied that no data is available with them regarding this matter. To the
question on furnishing the copy of CM’s approval for the said change of
alignment, the Monorail authorities replied that Metropolitan commissioner
sanctioned the change under the power conferred to him. The reply said, “The
Metropolitan commissioner visited the site on September 24, 2009 and instructed
to change the said alignment. Senior officer P.L. Kadu made the proposal, which
was sanctioned by the Metropolitan Commissioner on October 21, 2009.”
Mr Galgali has written a letter the chief
minister of Maharashtra demanding an enquiry into the role of the MMRDA
officers who made unscrupulous decisions which led to cost escalation and delay
of the project. “Due to the negligence of the MMRDA officers, the Monorail
project has been delayed for so long, which not only escalated the cost of the
project but also created traffic problems to lakhs of commuters.” said Mr
Galgali.
Dilip Kawathkar, joint project director, MMRDA
said, “Decisions are taken at the ground-level, keeping all the angles to
execute the project, including existing utility services.”