Monday, October 15, 2012

Land woes hold up parts of East-West Corridor in UP.

Indian Express: Lucknow: Monday, October 15, 2012.
More than a decade after work was started on the 3,300-km East-West Corridor by the Atal Bihari Vajpayee government, the UP section of the project is still languishing because of land acquisition-related issues.
As many as 653 km of the project passes through UP. Of the 21 stretches in state, only 17 have been completed so far, the UP regional office of the National Highways Authority of India (NHAI) has informed in reply to an RTI application.
The incomplete parts include a 1 km portion of the Lucknow-Kanpur stretch, a 1 km portion of the Orai-Jhansi stretch, a 3.82 km portion of the Jajmau Ganga bridge to Ramadevi crossing in Kanpur, and 1.7 km portion of the Bara to Orai stretch.
In its reply, NHAI has anticipated completion of the Jajmau Ganga bridge to Ramadevi crossing stretch in March 2013 while the other three stretches are expected to be completed in December.
Official said that the project got delayed because of land acquisition-related problems. In the Bara to Orai stretch, land for a 1.7-km portion in Kalpi town had not been handed over to NHAI yet. The work on the site was started in October 2006 and it was scheduled to finish in April 2009. While most parts of the 62.8-km stretch was completed on time, this portion remained a problem because of a dispute between the district administration and local residents over the land earmarked for the highway.
“The land required for that 1.7-km portion is owned by the state government on paper. But there are a number of families that have permanent constructions there. They are demanding money to vacate the land,” said an official.
Of the 51-km Orai-Jhansi stretch, work on 50 km is complete. Around 1 km highway is incomplete because of delay in obtaining clearance from the Forest Department and Ministry of Environment and Forests (MoEF).
The RTI reply said that construction of the highway was started here in 2005. An official said that the Forest Department of the UP government in 2010 raised objection on construction on an 800-metre stretch near Panwari, claiming that the land was notified as “forest protected land”.
“Permission was obtained for construction on that land both from the state government and MoEF in March this year. The project is likely to be complete in February next year,” an official said.
On the 5.46-km stretch of Jajmau Ganga Bridge to Ramadevi crossing on NH 25, the construction was delayed because the district administration handed over the land to NHAI very late.
Work on the stretch had started in 2005 and was scheduled to be complete in September 2008.
“Land was handed over to NHAI very late. Delay in obtaining clearance from Archeological Survey of India for construction near the protected Jajmau Teela in 2010 also delayed the work,” said Naveen Mishra, Project Director. “Now the cost of the project has increased manifold in the past few years while the payments are being done at the rate of 2005,” said an official.
On the Lucknow-Kanpur stretch, only one railway overbridge-cum-underpass is incomplete in Unnao district. NHAI Deputy General Manager Pawan Verma said that nearly 80 per cent of the ROB is complete and 20 per cent is pending because permission for earth mining from nearby fields could not be obtained during rainy season. “Work will resume when the administration issues permission,” Verma said.